Electrical Cable Size Calculator ⚡

Size copper or aluminium conductors by current-carrying capacity and voltage drop, with temperature & grouping derating and full breaker coordination (Ib ≤ In ≤ Iz). Based on IEC 60364-5-52 and NEC Article 310.

📊 Input Parameters

Leave 0/empty to skip voltage-drop check

📊 Results

Enter the load current and click Calculate

📚 References

Complete Guide to Electrical Cable Sizing

Choosing the right cable size is one of the most important decisions in any electrical installation. Get it wrong and you risk overheating, nuisance tripping, equipment malfunction, energy waste, or fire. This guide explains exactly how professional engineers size cables, and how this calculator applies those rules using NEC and IEC standards.

The Two Tests Every Cable Must Pass

A conductor is only correctly sized when it satisfies both of the following. The larger of the two results is the size you install.

1. Current-carrying capacity (ampacity). The cable must safely carry the current without exceeding its insulation temperature. The tabulated ampacity is reduced by derating factors, and the result (Iz) must be at least the rating of the protective device (In).

2. Voltage drop. Resistance and reactance cause the voltage to fall along the run. Excessive drop dims lighting, weakens motor torque, and trips controls. Limits are typically 3% for final circuits and 5% overall.

Breaker Coordination: Ib ≤ In ≤ Iz

This single inequality underpins safe sizing:

If Iz falls below In, the breaker could allow current the cable can't handle, letting it overheat before the device trips. The calculator above selects the breaker first, then the smallest standard cable whose derated ampacity clears it.

Derating (Correction) Factors

Catalogue ampacities assume about 30°C ambient and a single circuit. Real installations are rarely ideal, so the rated value is multiplied by correction factors:

Temperature: hotter surroundings reduce how much heat the cable can shed. Factors come from NEC Table 310.15(B)(1) / IEC 60364-5-52 Table B.52.14.

Grouping / bunching: cables packed together in a conduit or tray warm each other. Reduction factors come from NEC Table 310.15(C)(1) / IEC Table B.52.17.

Installation method & insulation: XLPE (90°C) carries more current than PVC (70°C) for the same size; clipped-direct runs carry more than buried-in-insulation runs.

Voltage Drop Formula Used

This tool uses the AC voltage-drop relationship including power factor and an allowance for conductor reactance, rather than resistance alone:

Single phase:  VD = 2 × I × L × (R·cosφ + X·sinφ)
Three phase:   VD = √3 × I × L × (R·cosφ + X·sinφ)

R = ρ ÷ A  (Ω/m),  ρCu ≈ 0.0225,  ρAl ≈ 0.036 Ω·mm²/m  (at operating temp)
X ≈ 0.00008 Ω/m,  A = cross-section (mm²),  L = one-way length (m)

VD% = (VD ÷ system voltage) × 100. Using power factor and reactance matters on large feeders, where ignoring them can underestimate the drop.

Copper vs Aluminium

Copper conducts better, so for a given current it needs a smaller cross-section and produces less voltage drop — ideal for final circuits and tight routes. Aluminium is lighter and cheaper per amp, which makes it popular for large feeders and risers, but it typically needs one to two sizes larger and careful terminations. The calculator includes standard ampacities for both (aluminium from 16 mm² upward).

Standard Cable Sizes & Ampacities

Reference values used by this tool (IEC 60364-5-52, method C, copper at 30°C, single circuit):

Size (mm²)AWG / kcmilPVC (A)XLPE (A)Typical use
1.5 16 17.5 23 Lighting circuits
2.5 14 24 31 General socket outlets
4 12 32 42 Heavy appliances
6 10 41 54 Sub-circuits, AC units
10 8 57 75 Cookers, large motors
16 6 76 100 Sub-mains / feeders
25 4 101 133 Distribution feeders
35 2 125 164 Feeders
50 1 151 198 Main feeders
70 2/0 192 253 Sub-mains
95 3/0 232 306 Risers
120 4/0 269 354 Risers / incomers
150 300 309 407 Main incomers
185 350 353 464 Main incomers
240 500 415 546 Transformer / main runs

These are reference figures for guidance. Actual ampacity depends on the exact installation method, cable construction and local code — always verify against the manufacturer's data and applicable regulations.

Worked Example

A 3-phase 415 V motor draws 50 A, fed by a 60 m copper PVC cable, 40°C ambient, with three other circuits bunched, 3% drop allowed, PF 0.85:

Enter these values above to see the full result and which criterion governs.

Common Mistakes to Avoid

Frequently Asked Questions

How do I calculate the correct cable size?

Cable size is determined by two checks: current-carrying capacity (the derated ampacity must be at least the protective device rating) and voltage drop (typically kept under 3% for branch circuits, 5% total). The larger size of the two governs. This calculator evaluates both and applies temperature and grouping derating per IEC 60364-5-52.

What is the maximum allowable voltage drop?

A common rule is 3% for lighting and final sub-circuits and up to 5% from the origin of the installation to the load. NEC recommends 3% on a branch circuit and 5% total (feeder + branch). Always confirm the limit required by your local code or project specification.

Should I use copper or aluminium cable?

Copper has higher conductivity, so for the same current it needs a smaller cross-section and gives lower voltage drop. Aluminium is lighter and cheaper, but for the same ampacity needs roughly one to two sizes larger. Aluminium is common for large feeders and distribution; copper dominates final circuits.

What is a derating (correction) factor?

Tabulated ampacities assume ideal conditions (about 30°C ambient, one circuit). When the ambient is hotter or several cables are bunched together, the safe current is reduced by multiplying by temperature and grouping factors. The derated ampacity is what must exceed the breaker rating.

Why does the breaker rating matter for cable sizing?

Correct coordination requires design current ≤ breaker rating ≤ cable ampacity (Ib ≤ In ≤ Iz). The cable must be able to carry whatever current the breaker will let pass before tripping, otherwise the conductor can overheat without the breaker operating.

Does this tool replace a qualified engineer?

No. It gives a fast, standards-based estimate for planning and checking. Final design must account for short-circuit withstand, earth-fault loop impedance, installation method specifics, harmonics and local regulations, and should be verified by a competent person.